If 8 men working 9 hours a day can build a wall 18 meters long, 2 meters wide and 12 meters high in 10 days, how many men will be required to build a wall 32 meters long, 3 meters wide and 9 meters high by working 6 hours a day in 8 days?

Share this post


Link to post
Share on other sites

 

If 8 men working 9 hours a day can build a wall 18 meters long, 2 meters wide and 12 meters high in 10 days, how many men will be required to build a wall 32 meters long, 3 meters wide and 9 meters high by working 6 hours a day in 8 days?

Are they men being the best they can?

Share this post


Link to post
Share on other sites

I gave myself 2 minutes to think on this. I'm guessing 30.

 

It took 720 hours to make the first wall. The second wall would take 1440 hours under that scenario.

 

8*6*x=1440

 

If it's wrong, oh well, been a while. :dunno:

Share this post


Link to post
Share on other sites

I gave myself 2 minutes to think on this. I'm guessing 30.

 

It took 720 hours to make the first wall. The second wall would take 1440 hours under that scenario.

 

8*6*x=1440

 

If it's wrong, oh well, been a while. :dunno:

 

I was going to try and do the problem while I was exporting some work...but no, someone walked and had me fix their work...WTF...don't these people know I have GC business to attend to. :mad:

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
Sign in to follow this  

×